Installation And Wiring; Sequence Of Installation - EBS CPX200NB Installation And Programming Manual

Alarm control unit
Hide thumbs Also See for CPX200NB:
Table of Contents

Advertisement

3. INSTALLATION AND WIRING

3.1. SEQUENCE OF INSTALLATION

1. Develop installation diagram accounting for the location of control unit, keypad,
detectors and other system components.
2. Install the control unit in hardly accessible place with uninterrupted power supply
ensured.
3. Install the keypad in a location convenient for a user and connect it with the control unit.
For description of keypad installation, please refer to chapter 3.6.2.
NOTE: Maximum length of cables connecting the control unit with the
keypad, at the core diameter 0.5mm2 cannot exceed 200m.
4. Install detectors and door and window reed relays. Connect the installed elements with
control unit. For sample configuration of zones, please refer to chapter 3.4.
5. Install and connect signalling devices with the control unit. For sample signalling devices
connection diagrams, please refer to chapter 3.5.
6. Complete the remaining cable connections.
7. Connect power supply and a battery with the control unit.
8. Program the functions of the control unit. Programming procedure was described in the
chapters below.
NOTE: If you use more than one keyboard in the system, be sure to
address each assignment of the keyboard (see ch. 3.6.4).
9. Verify the operation of the system and all its components.
CPX200NB ALARM CONTROL UNIT – INSTALLER MANUAL
9 / 116

Advertisement

Table of Contents
loading

Table of Contents