Closeout Instructions

Closeout Procedure

1. Refer to Figure 36, and INSTALL door decals.
2. IF PUSH AND GO is enabled, APPLY "PUSH TO
OPERATE" and "PULL TO OPERATE" labels as
shown in Figure 36.
3. ENSURE all connectors are secure.
4. ENSURE all wires are secured and hidden where
possible.
5. ENSURE the operator dress cover is installed and
secure.
6. ENSURE the controller cover is installed and
secure.
Figure 36
7. ENSURE the door and door trim surfaces are
clean.
8. ENSURE the door installation area is clean and
free of debris.
9. ENSURE that the client/resident is instructed on
how to operate the product correctly, and
understands how to perform the daily safety check.
10. COMPLETE Work Order and REPORT your actions
to Building Superintendent.