Initial Startup; Completing The Installation Checklist - Eaton 9390 Installation And Operation Manual

40–80 kva ups, integrated distribution cabinet
Hide thumbs Also See for 9390:
Table of Contents

Advertisement

Installing the IDC
3.
If not already removed, remove the doors. Remove the retaining screws located inside each door at the
top and bottom hinge pivot points, then lift the door off. Save the retaining screws for reinstallation of the
doors.
4.
If not already open, remove the screws securing the inside distribution panel doors, and swing the doors
open.
5.
If not already removed, remove the screws securing the top internal safety shield, and remove the shield
to gain access to the terminals.
6.
Route and connect the bypass breaker wiring from the IDC to the UPS cabinet. See Appendix 9 and refer
to the Eaton 9390 UPS (40–80 kVA) Installation and Operation Manual for UPS cabinet terminal locations.
7 .
To install the IDC MBP breaker shunt trip, remove the IDC top or bottom conduit landing plate to drill or
punch conduit holes, or remove knockouts. (see Drawing 164201690-6 on page 9-19).
8.
Reinstall the conduit landing plate and install the conduit.
9.
To locate appropriate terminals, and for wiring and termination requirements, see Drawing 164201690-9,
starting on page 9-33, and refer to the Eaton 9390 UPS (40–80 kVA) Installation and Operation Manual for
UPS cabinet terminal locations.
10. Route and connect the wiring.
11. When all wiring is complete, reinstall the safety shields.
12. Close the inside distribution panel doors and secure with the retained screws.
13. Reinstall the front doors.
14. Close the front doors and secure the latch.
3.4

Initial Startup

Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms as specified on page 8-1 become void. This service is offered as part of the sales contract for
the UPS system. Contact your Eaton service representative in advance (usually a two-week notice is required)
to reserve a preferred startup date.
3.5

Completing the Installation Checklist

The final step in installing the IDC is completing the following installation checklist. This checklist ensures that
you have completely installed all hardware, cables, and other equipment. Completing all items listed on the
checklist will ensure a smooth installation. Make a copy of the installation checklist before filling it out, and
retain the original.
After the installation is complete, a service representative will be able to verify the UPS system operation and
commission it to support the critical load. The service representative cannot perform any installation tasks
other than verifying software and operating setup parameters. Service personnel may request a copy of the
completed installation checklist to verify that all applicable equipment installations have been completed.
Note:
The installation checklist MUST be completed prior to starting the UPS system for the first time.
Installation Checklist
o
All packing materials and restraints have been removed from each cabinet.
o
Each cabinet in the UPS system is placed in its final installation location.
o
Shipping brackets are installed on cabinet and bolted to the floor for permanent installations.
o
All conduits and cables are properly routed to the IDC.
o
All power cables are properly sized and terminated.
o
Distribution panel branch circuit breakers are installed and wired to the load. (OPTIONAL)
o
IDC MBP breaker shunt trip signal wiring is connected from the IDC to the remote emergency power-off
(REPO). (OPTIONAL)
o
IDC maintenance bypass aux contact signal wiring is connected from the IDC to the UPS.
3-12
Eaton 9390 IDC (40–80 kVA) Installation and Operation Manual 164201690 Rev 3 www.eaton.com/powerquality