Commissioning
9.1
General
Commissioning requirements
S You will need the following:
S The mechanical and electrical installation of the system must be completed.
Commissioning sequence
To commission the SINUMERIK 802D sl, proceed as follows:
1. Check that the PCU boots.
2. Set the language.
3. Setting the technology
4. Set the general machine data.
5. Start up the PLC.
6. Start up the drive.
7. Set the axis/spindle-specific machine data.
8. Perform a dry run for the axes and for the spindle.
9. Optimize the drive.
10.Complete the commissioning; perform a data backup.
Siemens Automation Parts
SINUMERIK 802D sl Instruction Manual (BA), 05/2005 Edition
6FC5 397-0CP10-1BA0
– SINUMERIK 802D sl User Documentation
– SINUMERIK 802D sl Description of Functions
– A PC for commissioning and data backup
– Tools installed from the Toolbox CD:
RCS802D Commissioning and Diagnostic Tool
PLC802 Programming Tool
802D sl Configuration Data
PLC Library
STARTER (for optimizing the drive)
Adobe Acrobat Reader
– Match the encoder to the axis/spindle.
– Match the setpoint to the axis/spindle.
9