Prepare for Inspection Operation

Once the car is running safely on construction operation, you should next install all safety string
components in accordance with the job drawings package. The actual equipment in the string
may vary from job to job but for the Motion 4000 generally includes:
• Hoistway safety string -
• Governor switch
• Final Limit switches
• Buffer switches
• Compensation sheave switch
• Pit stop switch
• Cartop safety string -
• Safety clamp switch
• Emergency exit contact
• Cartop Inspection station and Stop switch
• In-Car Stop switch (in COP)
• Hoistway Switches
At this point, you should also:
• Install seismic equipment
Prepare for Inspection Operation
2
2-51

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Motion 4000 and is the answer not in the manual?

Questions and answers

Related Products for Motion Control Engineering Motion 4000

Table of Contents

Save PDF