Perfect grounding of all conductive parts such as fl oors, walls, roofs, barriers, work pieces,
transport devices, coating product tank, coating product supply or construction parts
in the spray area with exception of the high-voltage parts during normal operation is
important for optimum coating and safety.
Parts of the booth must be grounded in accordance with EN 12215.
Discharge of electrostatically charged components in
atmospheres containing solvents!
Explosion hazard from electrostatic sparks or fl ames.
Heavy paint mist if grounding is insuffi cient!
Danger of poisoning.
Insuffi cient paint application quality.
A poorly grounded work piece causes:
- very bad wrap around,
- uneven coating,
- back spraying to the spray gun (contamination) and coater.
Prerequisites for perfect grounding and coating are:
- Clean work piece suspension.
- Grounding of spray booth, conveyor system and suspension on the building side in
accordance with the operating manuals or the manufacturer's information.
- Grounding of all conductive parts within the working area.
- The grounding resistance of the work piece must not exceed 1 MΩ (megohm).
(Resistance to ground measured at 500 V or 1000 V).
- Connect the control unit to the signal ground.
- Mount spray gun to an grounded gun mounting.
- Connect all ground cables using a short and direct route.
- Safety shoes must be static dissipative.
ORDER NUMBER DOC2360924
WARNING
Ground all device components.
Ground the work pieces to be coated.
WARNING
Ground all device components.
Ground the work pieces to be coated.