4.8.2 Start sequence
The following drawings illustrate the start sequences of the genset with normal start prepare and extended
start prepare.
No matter the choice of start prepare function, the run coil is activated before the start relay (starter). The time
between the run coil and the start relay is setup in parameter 6151. In the following drawings this time is set
to 1 sec.
Start prepare
Crank (starter)
Run coil
Stop coil
Running feedback
1st start attempt
DEIF A/S
Start sequence:
Normal start prepare
t
OFF
1 sec.
2nd start attempt
t
OFF
3rd start attempt
Functional descriptions