Guide For Commissioning Of Et 200S With Fail-Safe Modules - Siemens SIMATIC ET 200S Installation And Operating Manual

Distributed i/o system - fail-safe modules
Hide thumbs Also See for SIMATIC ET 200S:
Table of Contents

Advertisement

1.4

Guide for Commissioning of ET 200S with Fail-Safe Modules

1.4
Introduction
The following table lists all important steps required for commissioning ET 200S distributed
I/O systems with fail-safe modules as DP slaves/IO devices on PROFIBUS DP/
PROFINET IO.
Steps from Selecting the F-Modules to Commissioning ET 200S
Table 1-3
Step
1.
2.
3.
4.
5.
6.
7.
Note
You must configure and assign parameters to the F-modules in
commissioning.
This is required because the PROFIsafe addresses of F-modules are assigned automatically
by
switches before mounting the module.
ET 200S Distributed I/O System - Fail-Safe Modules
Hardware Installation and Operating Manual, 07/2005, A5E00103686-04
Steps from Selecting the F-Modules to Commissioning ET 200S
Procedure
Select F-modules for ET 200S configuration "Configuration Options" chapter
Configure and assign parameters to
STEP 7
F-modules in
Set PROFIsafe addresses on F-modules
Mount ET 200S
Wire ET 200S
Commission ET 200S on
PROFIBUS DP/PROFINET IO
If commissioning was not successful,
perform diagnostics on ET 200S
STEP 7
. You must set these PROFIsafe addresses on each F-module by means of
1.4 Guide for Commissioning of ET 200S with Fail-Safe Modules
See ...
"Configuration and Parameter Assignment"
and "Fail-Safe Modules" chapters
"Address Assignment and Installation"
chapter
"Address Assignment and Installation"
chapter
"Wiring and Fitting Modules" chapter
ET 200S Distributed I/O system
"Diagnostics" chapter, "Fail-Safe Modules"
ET 200S Distributed I/O System
chapter and
manual
STEP 7
before
Product Overview
manual
1-5

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents