4. Press the [START] button to begin the Vertical Bar Calibration test.
NOTE: QAP requires that the system be in an idle state (without exposures) for at least 10 minutes before
the Vertical Bar Calibration portion of the test can begin. If the system has not been idle, a
countdown timer appears on the bottom of the screen and Vertical Bar Calibration will begin
automatically when the specified time has been reached.
Figure 11-12 Vertical Bar Calibration screen
5. Wait for the test to complete.
The Detector Check Tests screen appears.
6. Follow the instructions on screen to complete this portion of the test:
Figure 11-13 Detector Check Tests screen
a) Press [START] and wait for the detector check tests to be completed and results to be displayed.
The Detector QC Tests screen appears automatically when the Detector Check Tests are complete.
7. Follow the instructions on screen to complete this portion of the test:
Definium 5000 X-Ray System
Operator Manual
Chapter 11: Quality Assurance Process and Maintenance
5197809-1EN
Rev. 4 (13 February 2008)
© 2008 General Electric Company. All rights reserved.