Site Preparation Checklist for the SRX5400 Firewall

The checklist in
Table 28 on page 143
for firewall installation.
Table 28: Site Preparation Checklist
Item or Task
Verify that environmental factors such
as temperature and humidity do not
exceed firewall tolerances.
Select the type of rack or cabinet.
Plan rack or cabinet location, including
required space clearances.
Plan electrical power provisions.
If a rack is used, secure rack to floor
and building structure.
Acquire cables and connectors.
Locate sites for connection of system
grounding.
Measure distance between external
power sources and firewall installation
site.
summarizes the tasks you need to perform when preparing a site
For More Information ...
"SRX5400 Firewall Environmental
Specifications" on page 144
"SRX5400 Firewall Cabinet Size and Clearance
Requirements" on page
149,
"SRX5400 Firewall Rack Size and Strength
Requirements" on page 148
"Clearance Requirements for SRX5400 Firewall
Airflow and Hardware Maintenance" on page
147
"Calculating Power Requirements for the
SRX5400 Firewall" on page 150
"Connection to Building Structure for the
SRX5400 Firewall Rack" on page 149
DC Power Electrical Safety Guidelines and
Warnings