Positioning and leveling equipment
Contents
Positioning and leveling the equipment
This section contains information on the following topic:
Positioning and leveling the equipment . . . . . . . . . . . . . . . . . . . . . . . .
Columns normally stand on adjustable feet that provide leveling capability
and ground isolation. However, casters are available and can be used for
two-tier columns. If a third module is added to a column with casters, the
casters must be replaced with leveling feet.
Note: If earthquake bracing is required, go to "Installing earthquake
bracing" on
page 297
and level equipment. When those procedures are complete, return to
Step 4 or Step 5 (as applicable) in the initial installation procedure.
Use Procedure 3 to position and level the equipment.
Procedure 3
Positioning and leveling the equipment
1
Check the equipment room floor plan to position columns.
2
Level the column.
a.
Remove the front and rear exhaust grills.
b.
Remove the front and rear air intake grills.
to install column and floor bracing, and to position