Preparing to power up
Connecting the ac power source
553-3021-210
Standard 1.00
Powering up the system and initial loading
Follow Procedure 48 to prepare to power up a Large System.
CAUTION
Verify that the safety grounds are properly connected.
Procedure 48
Preparing to power up
1
Set the ac service panel circuit breakers OFF.
2
Set the main circuit breakers in the rear of each pedestal OFF.
3
Set the power supply or MPDU switches in each module OFF.
4
Set the ringing generators in each IPE or PE module OFF.
5
Set the blower unit switch in the front of each pedestal OFF.
6
Set all faceplate switches to ENB.
To connect a Large System to the ac power source, follow one of the two
options below.
Procedure 49
Option 1: Using the installed power plug (recommended)
Each column can be directly connected to the ac power source.
1
Connect the power plug from each column to the ac power respectable.
2
Proceed to "Turning ac power ON" on
October 2003
End of Procedure
page
267.
End of Procedure