Step 9 Install the processor carrier to the conjoined heat sink.
1.
Issue 17 (2021-03-09)
Figure 8-37 Pasting patterns
Use a clean card or blade to smear the thermal compound over the entire
center of the CPU.
The thickness of the thermal compound is about that of a piece of ordinary
paper. Ensure that the thermal compound is evenly and fully coated.
Figure 8-38 Smeared thermal compound layer
Aligning the processor corner with a triangle mark with the corner of the heat
sink with a notched triangle, buckle the processor carrier on the heat sink.