FusionServer Pro XH321 V5 Server Node
Maintenance and Service Guide
Figure 8-20 Removing a supercapacitor holder
Step 7 Remove the cable between the supercapacitor and the RAID controller card.
Step 8 Remove the supercapacitor from the holder.
Figure 8-21 Removing a supercapacitor
Step 9 Place the removed component in an ESD bag.
Place only one component in an ESD bag.
----End

8.4.6 Installing the Supercapacitor

Procedure
Step 1 Power off the server node.
For details, see
Issue 17 (2021-03-09)
NO TICE
8.3.2 Power-Off
Copyright © Huawei Technologies Co., Ltd.
Procedure.
8 Parts Replacement