Commissioning

4.1

Typical commissioning scenarios

After installation, you need to commission the inverter to set the inverter functions such that
the inverter/motor combination is best adapted to the drive task.
The inverter's functions and parameters are accessed either via the Operator Panel (BOP-2
or IOP) or the STARTER commissioning tool from a PC.
An inverter can also be commissioned by saving the settings of an inverter (which has been
fully commissioned) onto a memory card (see External data backup and series
commissioning (Page 86)) or the Operator Panel or using STARTER in the PC and then
transferring (upload and download) them to another inverter used for the same drive task.
Note
Should anything go wrong during commissioning ...
If you are not able to complete commissioning for any reason, be it due to line voltage failure
or because you made an error when setting the parameters and can no longer reproduce the
individual settings or do not know whether the inverter has been used before, you can
restore the inverter to the factory settings. See Restoring the factory setting (Page 92).
Inverter with CU240B-2 and CU240E-2 Control Units
Operating Instructions, 07/2010, FW 4.3.2, A5E02299792B AA
4
55

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics g120 cu240e-2Sinamics g120 cu240b-2 dpSinamics g120 cu240e-2 dpSinamics g120 cu240e-2 fSinamics g120 cu240e-2 dp-f

Table of Contents