B.7 Ferrite Clamp Installation Procedure
Purpose
This procedure ensures that unwanted radio frequency noise is filtered, which is required for CE
compliance.
Parts needed
Part #
047260
089037
Procedure
Step
1
Disconnect all power to the instrument.
2
Allow 3" to 4" of extra slack in the wires.
3
Group all analog input wires together.
4
Open the ferrite cable clamp by gently prying up on the clasp located on the side of the clamp.
5
With the clamp approximately 3/4" to 1" from the instrument's terminals, lay the analog input wires in
the groove of the clamp.
6
Snap the clamp closed, making sure to not pinch the wires.
7
Secure the wires by affixing a cable tie around the wires near each end of the clamp.
8
Trim the cable tie but leave a "tail" of approximately 1".
9
Repeat steps 1-8 for the analog output wires.
12/00
Quantity
2
4
AI wires
3/4" to 1"
Instrument
AO wires

Figure Appendix B-5 Ferrite Clamp Installation

VPR & VRX – User Manual
Ferrite cable clamps
Action
Ferrite clamp
Cable tie
Cable tie
Appendix B
Description
Nylon cable ties
303

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vrx100Vrx150

Table of Contents