SMA Sunny Island SI3300 Installation & Operating Instructions Manual page 74

Bidirectional battery inverter for stand-alone applications
Table of Contents

Advertisement

Sunny Island
The Sunny Island can control ecopower Mini combined heat and power units of the
company VALENTIN Energie- und Umwelttechnik GmbH.
If one or more CHPs are available in the system, the corresponding values must be
set in the menu „PARGRD" (3+4). The CHP is controlled via the serial RS232 inter-
face COM3 of the Sunny Island.
The menu „BHKW" (2+5) is primarily used for the display of the CHP´s operating
state. In addition, it can be used for the commissioning of the plant to manually
switch on and off the CHP with special inputs. All inputs are only valid until the menu
is quit. The menu items are:
Menu Item
BHKWSTATE
PBHKW
PBHKWMAX
PBHKWSET
BHKWMODE
Table 7.2: Settings in the menu „BHKW" (2+5)
BWRI33-12:EE
Fig. 7.6: Menu „BHKW" (2+5)
State, meaning see CHP documentation
Effective power, can be set
Total power capacity of all connected CHPs
Power input, can be set
Operating mode, can be set, meaning see CHP documentation
- 74 -
Installation & Operating Instructions
Meaning
SMA Regelsysteme GmbH

Advertisement

Table of Contents
loading

Table of Contents