SMA Sunny Island SI3300 Installation & Operating Instructions Manual page 142

Bidirectional battery inverter for stand-alone applications
Table of Contents

Advertisement

Sunny Island
„PARALL" (3+9)
Parameter
Unit Min. Max.
706_Man K6
707_Man K7
708_Man K8
710_K1 t2 begin
711_K1 t2 end
BWRI33-12:EE
Default
0
9
0
0
2
0
0
2
0
h
0
23
0
h
0
23
0
Installation & Operating Instructions
Description
Operating mode of relay K6
0: OFF:
Switch relay K6 off
1: ON:
Switch relay K6 on
2: AUTO:
Sunny Island automatically con-
trols relay K6.
3: RUN:
Relay is only switched on when
the Sunny Island operates.
4: RUN_U:
Relay is only switched on when
the Sunny Island operates as
the grid–forming element.
5: RUN_I:
Relay is only switched on when
the Sunny Island is in "grid-tied
operation".
6: HD_CTRL:
Relay is switched during trans-
fer from grid-forming to grid-tied
operation.
7: TK_CTRL:
Relay is switched during trans-
fer from grid-tied to grid-forming
operation.
8: HDTK_CTRL:
Relay is switched during any
transfer from grid-tied to grid-
forming operation or vice versa.
9: GEN_MANU:
Relay is switched if generator
has already been started before
the Sunny Island.
11: LOAD:
Relay is switched in relation to
load (see also parameter 625 to
630)
Operating mode of relay K7
0: OFF:
Switch relay K7 off
1: ON:
Switch relay K7 on
2: AUTO:
Sunny Island automatically con-
trols relay K7.
Operating mode of relay K8
0: OFF:
Switch relay K8 off
1: ON:
Switch relay K8 on
2: AUTO:
Sunny Island automatically con-
trols relay K8.
Start of special period t2 for K1
End of special period t2 for K1
- 142 -