Siemens SIMATIC ET 200pro FC-2 Operating Instructions Manual page 91

Low voltage converter for the distributed i/o system
Hide thumbs Also See for SIMATIC ET 200pro FC-2:
Table of Contents

Advertisement

4. Switch on the motor.
The inverter starts the motor data identification. This measurement can take several
minutes.
Depending on the setting, after motor data identification has been completed, the inverter
switches off the motor - or it accelerates it to the currently set setpoint.
5. If required, switch off the motor.
6. Relinquish the master control after the motor data identification.
7. Press button
You have completed the motor data identification.
Self-optimization of the speed control
If you have not only selected motor data identification with the motor stationary, but also
rotating measurement with self-optimization of the speed control, you must switch on the
motor again as described above and wait for the optimization run to finish.
Quick commissioning has been completed once the motor data identification has been
successfully completed.
SIMATIC ET 200pro FC-2 converter
Operating Instructions, 04/2018, FW V4.7 SP10, A5E34257324B AF
(RAM to ROM).
Commissioning
6.6 Quick commissioning
89