Change Information - Ericsson EDA 2530 Commissioning Instructions

Commissioning procedure for cable and wireless access
Table of Contents

Advertisement

14

Change Information

REV
DATE
PA1
08-11-2008
PA2
11-02-2009
PA3
15-02-2009
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
CHANGES/COMMENTS
First Draft Issue.
Second Draft Issue
Third Draft Issue
Changes resulting from commissioning the first EDA2530 FOA site at
CWA Norwich North LLU. The order in which the sections are performed
has been re-arranged to be as follows:-
Introduction (sec 1, unchanged)
EDA2530 MSAN Equipment (sec 2, unchanged)
Resources (sec 3, unchanged)
Commissioning requirements (sec 4, unchanged)
Initial Configuration (now sec 5 was sec 6)
IP Address of PC (now sec 5.1 was sec 6.1)
CP card CF Download (now sec 5.2 was sec 6.2)
Subrack Equipping (now sec 5.3 was sec 5)
Logon to LCT (now sec 5.4 was sec 6.3)
Restore CP to factory defaults (now sec 5.5 was sec 6.4)
Reset backplane eprom (now sec 5.6 was sec 6.5)
Check s/w inventory (now sec 5.7 was sec 8.1.3)
S/w download/upgrade (now sec 6 was sec 9)
Configure CP IP card (sec 7.1 to 7.12, unchanged)
EDA2530 equipment test & alarms checks (sec 8, unchanged)
Configure & test units (now sec 9 was sec 10)
Network Integration (now sec 10 was sec 11)
EDA 2530 Commissioning Procedure for Cable and Wireless Access
© Ericsson AB 2010
Commercial in confidence
193 (200)

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents