Placing the Switch on a Table or Shelf
The Summit switch comes with four self-adhesive rubber pads. You can place up to four Summit
switches on top of one another.
Apply the pads to the underside of each switch, and place a pad at each marked corner of the switch.
Place the switches on top of one another, ensuring that the corners align.
Verifying a Successful Installation
After you supply power to the Summit switch, the switch performs a power-on self test (POST).
During the POST:
• All ports are temporarily disabled
• The packet LED is off
• The power LED is on
• The MGMT LED flashes until the switch successfully passes the POST
If the switch passes the POST, the MGMT LED blinks at a slow rate (one blink per second). If the switch
fails the POST, the MGMT LED shows a solid yellow light.
NOTE
See Chapter 4 for more information about Summit LED activity.
Removing and Installing Summit48si AC Power Supplies
This section applies to the Summit48si switch AC power supplies only. The Summit48si comes with a
minimum of one power supply preinstalled at the factory. If you have a Summit48si switch, follow the
instructions in this section for removing and installing the Summit48si AC power supplies.
For information about removing and installing Summit48si DC power supplies, see "Installing the
Summit48si Switch DC Power Supply" on page 95.
NOTE
Summit48si power supplies must be serviced by trained service personnel.
NOTE
If you need to power down the switch, remove all of the power cords from the installed power supplies.
To remove a Summit48si AC power supply:
Extreme Networks Consolidated "i" Series Hardware Installation Guide
Removing and Installing Summit48si AC Power Supplies
91
Need help?
Do you have a question about the Summit Summit1i and is the answer not in the manual?
Questions and answers