DRYPOINT
®
RA III
8.2
Initial commissioning
For initial commissioning work to be carried out, the following protective equipment must be always worn
and the preparatory tasks must have been completed.
Tools
•
No tool necessary
Assembly of the product is complete.
1.
Compressed air inlet/outlet valves are closed.
2.
Electrical installation of the product is complete.
3.
The section "3.1 Product overview" on page 18 was
4.
The condensate drain service valve is open.
5.
The section "3.2 User Interface" on page 29 was
6.
Prerequisites
Material
•
No material necessary
Preparatory tasks
read and applied
read and applied
Original installa�on and opera�on manual
Protective equipment
.
.
67 | 118