10.8 Installing AC Input Power Cables for the
ETP48600-C5B1
Prerequisites
● Ensure that the upstream AC input circuit breakers are OFF, and attach warning
labels such as "Do not operate."
● Switch off all circuit breakers before installing the power cables.
Procedure
Step 1 Prepare AC input power cables and cord end terminals.
Step 2 Connect the AC input power cables to the corresponding AC input circuit breakers.
Figure 10-17 Installing AIU03 AC input power cables
(1) Reused DG
----End