3. Hang the wall mounting bracket on the expansion bolts and fasten it with flat washers, spring
washers, and nuts (Figure 3-14).

Figure 3-14: Hang Bracket

4. Hold the gNB vertically and align the two pins on the gNB bracket with the pin holes on the pole
mounting bracket. Push the eNB down until the hooks are firmly attached to the corresponding
slots on the pole mounting bracket. Then, tighten the screw to complete the installation
(Figure 3-15).

Figure 3-15: Completed Installation

5. Once the installation is complete, proceed to
section
3.4.