Henny Penny FlexFusion FM08-454-G Installation Manual page 27

Electric gold combi
Table of Contents

Advertisement

To prevent the unit from tilting, a special fastening kit is supplied by the
manufacturer or is available as an accessory.
The fastening kit contains two floor fasteners and all components
required to bolt or bond to the floor.
The unit or underframe is fastened by means of two floor fasteners as
shown in the drawing.
Floor without steam barrier
In the case of floors without a steam barrier, the floor plates are bolted
to the floor using the bolts provided.
A
e
Image: A: Position of floor plate; B: floor plate bolted to the floor
a Cap nut
b Holding plate
c Upright bolt
Prerequisite Floor capable of accommodating the weight of the unit
Floor must be clean and suitable for the manner fastening
Unit set up and aligned in accordance with the planning drawing
1. Insert the floor plate from the fastening kit into the retainer as
shown in the drawing.
2. Screw on the cap nuts hand-tight.
3. Align the floor fastener in position 1-1 or 2-2 on the unit leg or
underframe as shown in the drawing and mark the fastening holes
on the floor.
4. Mark the position of all unit legs or underframe on the floor.
5. Using suitable lifting equipment, move the unit so that the holes
can be drilled in the floor.
6. Drill holes with a diameter matching that of the anchor sufficiently
deep in the floor.
7. Carefully place the unit in the installation position.
8. Screw on cap nuts and remove the retainer from the floor plate.
9. Using the anchors and fastening screws provided, screw the floor
plate to the floor.
10.Ensure that a tight seal against the floor has been reestablished
after the fastening screws are installed.
a
b
c
d
Installation instructions
Installing the unit
B
f
d Floor plate
e Lag bolt
f Unit leg
27