Control Box; Mechanical Installation; Electrical Installation - Xylem FLYGT Pareo DCM 711 Installation, Operation And Maintenance Manual

Control module
Table of Contents

Advertisement

4.3 Control box

1
3~
1. Power supply
2. Control box
3. Pump

4.3.1 Mechanical installation

The control box is prepared to be installed on a wall.
Select one of the following actions:
Condition
Installation
with the pre-
drilled holes
Installation
with the
handle

4.3.2 Electrical installation

1. Check that the rating of the control box corresponds to the rating of the pump.
For more information, see
2. Check the power supply for current, voltage, and frequency.
For more information, see
DCM 711 Installation, Operation, and Maintenance Manual
2
3
Action
1. Drill four 6.5 mm (0.25 in) holes in the wall for the screws.
The image shows the drilling pattern.
193 mm
(7.6 in)
204 mm
(8.0 in)
2. Install the control box with M6 screws.
Use the handle to hang the control box on the wall.
Variants
on page 44.
Variants
on page 44.
4 Installation
19