2.
Insert new saw band in the guide cubes. Make sure the saw band runs between
both guide rollers and it is pushed all the way to the top.
3.
Put the saw band on both guide wheels. Make sure that the saw band ridge fits
tightly to the wheel rim. Then push the saw band as far back as possible.
4.
By turning the stretching star to the right, you will stretch the saw band slightly.
Remove the plastic cover of the saw band teeth.
5.
Close the cover of the arm.
6.
Install the yellow protective cover of the band. The arrow on the cover must match
the direction of the arrow on the band. If it does not, you must turn the band
round.

Saw band stretching and inspection

Right saw band stretching is one of the most important criteria's, which influents
accuracy and saw band service life. Stretch the saw bands according to the selected
saw band and the band saw. Keep the recommendation of your manufacturer.

Saw band stretching

1.
The saw band must not fall from the wheels after setting.
2.
Install the Tenzomat on the saw band and secure it with screws.
3.
Stretch the saw band until it is stretched to the recommended value

Saw band run adjustment on stretching wheel

Saw band run on the stretching wheel must be regularly inspected. The inspection has
to follow every saw band replacement.

Saw band run inspection

If the run is not correct, the following problems may occur:
The saw band falls from the wheels – The saw band and protective cover can
be damaged.
 
Manual version:
1.02 / Nov. 2011
Manual rev.: