1

Floor Space

Figure 4 Floor Space
Requirements
1

Floor Clearance

1

Floor Inclination

Site Requirements

This section describes the following installation site requirements for
the library:
• Floor space
• Floor clearance
• Floor inclination
• Floor strength
• Power
• Grounding
25"
(For Maintenance Only)
25"
71"
21.5"
25"
(For Maintenance Only)
The cabinet has a nominal floor clearance of 0.75 inch (1.9 cm). The
library should be placed on a level, uncarpeted floor free of cracks,
depressions, and so on.
The floor in the installation site must be level to within 0.25 inch over a
6 x 6 foot area.
ACL 4/52 Facilities Planning and Installation Guide
Chapter 1 Installation Requirements
128"
31.12"
(Ramp Side/Off-load Area)
Library
Site Requirements
1
72"
Front of Library