And check MBMS is working. The "STATUS" lamp will light green.
The Power Relays in BMS will switch ON after 30 seconds, when the MBMS was turned ON.
The "STATUS" lamp of the BMS will light green;
When the voltage distance is smaller than the parameter, the battery string will do the
parallel operation.
When the MBMS was turned ON, the "STATUS" lamp of the BMS will light red, but it is
normal;
Note: If the MBMS can't build communication with other equipment, the system can't
work normally. External Power should communicate with battery system through LAN,
CAN or RS485. Otherwise maybe cause battery system work abnormal.
Caution: The whole Battery Energy Storage System (BESS), after installation or restart
the system when long time not in using, should charge it to full at first.
Pour l'ensemble du système de stockage d'énergie de batterie (BESS) après l'installation ou le
redémarrage du système après une longue période d'inactivité, il faut le charger complètement
au début.
3.6.5 System turns off
During maintenance or long-term storage, must turn off the battery system:
For external power supply,
40