Hydraulic Flow Testing

The following procedure was performed on the right
hand wheel motor hoses. It can be performed on either
the right or left side of the machine.
Note: Cleanliness is a key factor in successful flow
testing of the hydraulic system. Thoroughly
clean all exposed surfaces prior to any type of
maintenance. Cleaning all parts with a solvent
wash and air drying is usually adequate.
As with any precision equipment, all parts
must be kept free of foreign material and
chemicals. Protect all exposed sealing areas
and open cavities from damage and foreign
material.

Hydraulic Flow Testing Procedure

1. Lift the back of the unit so the side being tested is off
the ground. Place jack stands under the rear frame
to support the unit. Remove the rear tire (Fig. 336).
Note: Be careful not to place jack stands near any
moving parts or areas not capable of sup-
porting the weight of the machine.
Fig 336
Z580/Z589 DFI Z Master Service Manual
HYDRAULIC SYSTEM
2. Clean any dirt or debris away from the hydraulic line
fittings. Mark each of the hoses and fittings so they
will be properly re-installed after testing. Remove the
hydraulic lines.
Note: Cap the fittings to prevent dirt from entering
the hydraulic system (Fig. 337).
PICT-3494a
Fig 337
PICT-3496a
4
4-33

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Z589 dfi z master742537425474253cp74254cp

Table of Contents