7.5 Meter & CT Connection
7.5.1 CT Connection
The CT cables have been installed with SMILE-S5 when shipped.
Please take out 2 CTs (Grid CT and PV CT) provided as accessory.
Step 1: Buckle the Grid CT on the house-service live wire. The arrow of the Grid CT
should point to the Grid port of SMILE-S5.
Step 2: Buckle the PV CT on the grid live wire. The arrow of the PV CT should point
to the Grid port of PV inverter.
Step 3: Connect the CT cables to the Grid CT and PV CT respectively.
NOTE:
The CT cable marked Grid CT should be connected to the Grid CT, and the CT cable
marked PV CT should be connected to the PV CT.