3
3.1

Initial check-out

For an initial check-out of your Master/Slave configuration, verify as follows:
Is the mainframe installed properly: fuses, power selection, power cord connected?
l
Is the Master/Slave board installed properly?
l
Is the fiber-optic cable between the Master/Slave boards in the mainframes connected
l
properly?
Has the Master/Slave operating mode of the mainframe been set in the Perception
l
software?