Install the Server

Do not attempt to move the server alone without a lift. For a one-person installation,
Caution -
all the main CRUs must be removed, and a lift must be used. For a two-person installation, all
the CRUs must be removed, and a lift is optional.
1.
Prior to installing the server, confirm that you have removed the following
components.
Both processor modules
The main module
All four power supplies
All five fan modules
Refer to the SPARC T8-4 Server Service Manual for removal instructions.
If you are using a mechanical lift, ensure that the lift is level and stable.
2.
Lift the server up to the correct height.
3.
Ensure that the bottom edge of the server has cleared the bottom of the shelf rails.
Install the Server
Installing the Server