Connect A Terminal Or Emulator To The Ser Mgt Port - Oracle SPARC T8-4 Installation Manual

Hide thumbs Also See for SPARC T8-4:
Table of Contents

Advertisement

2.
Go to the rear of the server and locate the two grounding holes beneath fan
module 4 (FM4).
3.
Position and align the grounding lug on the two grounding holes at the rear of
the chassis.
4.
Secure the grounding lug to the grounding holes using the two M5 screws.
Secure the other end of the grounding wire to the earth ground in the building.
5.
You can secure the grounding wire to a proper grounding point on the rack, as long as the rack
is properly grounded to the earth ground in the building.
Related Information
"Rear Panel Components" on page 15
"Power on the Server for the First Time" on page 69

Connect a Terminal or Emulator to the SER MGT Port

Prior to powering on the server for the first time, make a serial connection to the SP from a
terminal or terminal emulator. After making this serial connection, you will be able to view the
system messages when you connect the power cords.
1.
Confirm that you have completed the following tasks:
Completed the preparation for installation.
a.
See
"Preparing for Installation" on page
Connect a Terminal or Emulator to the SER MGT Port
23.
Powering On the Server for the First Time
67