Steps in the commissioning process:
Following completion of all assembly and connection work as described in
6 „Assembly" on page 34 and
commissioning the control
Advanced-ETH" on page 46 (parameterisation and configuration), the system is ready for
commissioning.
1.
Determine the position.
2.
Assemble the DryExx® as described in
mounting
3.
Install the power supply and lines for the enabling signals.
4.
Complete the wiring of the DryExx® with the control.
5.
Set up the compressed air connection with the required air pressure 0.5 - 0.7 MPa
( 5 - 7 bar) and regulate the pressure regulator to the site conditions.
6.
Provide the dosing medium.
7.
Ventilate the dosing pump via the booster function on the control.
8.
Check that the connections are leakproof.
9.
Fill and bleed the pipe system
system" on page 45
10. After commissioning the control Test the plant.
8.1.1
Filling the pipe system
WARNING!
When carrying out refilling, commissioning and plant optimisation operations
ensure that no conveyor belt lubricant is allowed to drip onto the floor.
1.
Adjust the compressed air filter regulator for the control air of the pump
to approx. 0.3 - 0.35 MPa (3 - 3.5 bar).
2.
Open the vent valves in the tap line system.
3.
Starting of the application by activation of the individual lubrication circuits via the
manual booster function of the control unit.
unit DryExxEco
4.
Restarting of the "booster phase" until the conveyor belt lubricant comes out of the
nozzles.
5.
Repeat the process under step 3 "Booster phase", lubrication circuit for lubrication
circuit until the entire system is vented.
6.
Optimising the setting of the working air pressure of the pump, so that the nozzles
produce the correct spray pattern.
Ä Chapter 7 „Connection" on page 38 , as well as
Ä Chapter 8.2 „ Commissioning: control unit DryExxEco
®
" on page 36 .
Ä Chapter 8.1.1 „Filling the pipe
®
Advanced-ETH" on page 30).
Commissioning and operation
Commissioning: DryExx® > Filling the pipe system
Ä Chapter 6.2 „DryExx wall
Ä Chapter 5.2 „Description of the control
45
Ä Chapter
®