c o m m i S S i o n i n G
6. Ground cable of drive securely connected
at both ends and power cable shields
grounded at both ends
7. Line supply and motor cables not
connected at both ends (cables and drive
must be meggered before connection)
MV switchgear
1. Type of MV switchgear selected and
wired per ABB MV switchgear
specification
2. MV switchgear ready to be tested with
drive
3. MV switchgear protection relay settings
tested
4. Safety devices (door locks, Kirk® key,
grounding switch, etc.) tested and in
operation
5. MCB IS EXCLUSIVELY CONTROLLED BY
THE ABB DRIVE
Motor
1. Motor installed, aligned and alignment
protocol available
2. Motor not coupled to driven load
3. Ground connection completed
4. Motor auxiliaries (bearing lubrication,
heater cooling, etc.) ready
Insulation tests
1. All power cables to input transformer,
between input transformer and drive, and
from drive to motor are meggered, and
measured values are within the required
limits
2. Test report of the megger test available
Note: If the test is carried out by the
commissioning engineer of the drive, an
additional day per drive motor combination
needs to be reserved. The test must comply
with the specification.
Power supply
1. Medium voltage available for start-up of
drive
2. Low voltage auxiliary power available for
start-up of drive according to the
instructions in the User manual
Miscellaneous
1. Sufficient number and correct type of
spare parts available
2. Air conditioning of drive room ready for
load run of drive
3. Optional equipment ready