• Set the clock and date on the HMI display by pressing a random area of the screen
for 5 seconds. A popup menu will appear. Choose Show System Settings and go to
Time. Set the time and date and exit until the Home Page is displayed.
The water monitoring system will be now ready to operate. All sensors are delivered pre-
calibrated and after having adjusted the flow, the system will now display the actual values
of pH, Temperature, Turbidity, and PAH in the water.

5.2 WMR

Check points relevant for the installation of the WMR system are described in this section.
• Verify that the check list found in the section 7. Appendix in the installation manual
has been filled out.
• Inlet and outlet hoses are connected as specified with reference to the installation
layout.
• The flow paths to and from the system are not blocked.
• The power supply connections are as specified in the Electrical Drawings.
• Protective earth is connected.
• Cut off the small rubber tip on top of the manometer. However, do not remove the
black rubber part.
• Open the flow regulator valve inside the WMR cabinet to the middle position (i.e.
turn the valve to the outer position and turn the valve 4 turns in the opposite
direction).
• Start sampling by pressing the RUN button in the bottom right corner of the home
page on the WM system.
• The WMR pressure setting is delivered pre-adjusted. If flow alarm occurs during
initial start-up, it indicates that the installation requires more pressure to create a
higher flow. This can be done by increasing the pressure on the pressure reduction
valve. Please look at the manometer to ensure that the maximum allowable pressure
is not exceeded. Observe that a flow is established and that no flow alarm occurs.