STEP
1
Check unit supplied is as per works order
2
Check unit contains correct IO cards.
Check unit has the correct firmware loaded
3
into the Flash memory.
STEP
4
Set up card address switches
5
Set up modem power selection
7
Set up 120/230V AC operation selection
Enable RTC battery and confirm the
8
watchdog link is correctly installed
Install unit and connect safety earth lead to
9
cabinet earth point
10
Connect digital IO
11
Complete post installation check
12
Identify all connectors/cable forms
13
Connect all connectors to the unit
14
Connect the unit to mains outlet
15
Switch on unit supply
16
Connect unit support battery
7
17
Commission the application
THE REST OF SECTION 4 TAKES YOU THROUGH THE STEPS IN THE
INSTALLATION CHECKLIST (above) IN MORE DETAIL...
Section 4.2 takes you through the steps that 'configure' the hardware before the unit is
installed.
Sections 4.3, 4.4 and 4.5 take you through the steps to install the unit.
And finally, section 4.6 takes you through all the steps involved in connecting up all the
various interfaces to the unit.
The unit, prior to its installation and commissioning, requires configuring for the type of
application, either on site or at a depot.
The hardware has a number of options as follows, which require selection before power
is applied to the unit...
667/HB/31601/000
PRE-INSTALLATION CHECKLIST
FUNCTION
INSTALLATION CHECKLIST
FUNCTION

4.2 SET-UP

Page 24
UTMC OTU/MOVA Handbook
REFERENCE
WORKS ORDER
WORKS ORDER
2.2
REFERENCE
4.2.1
4.2.2
4.2.3
4.2.4
4.3 to 4.5
4.6.2
4.6.3
4.6.4
4.6.5
4.6.6
6 and 7
Issue 5