Verify routing and installation of field control wiring per installation instructions
Verify proper connection of optional CCN or BACnet wiring per installation instructions
(Temporarily disconnect this wiring for start-up; reconnect once unit is started)
Verify proper installation of plenum rated pneumatic pressure tubing to building pressure and supply fan static pressure transducers
per installation instructions
Verify that all pencil-type thermistors are fully inserted into corresponding wells
Check gas piping for leaks (48N only) and correct as needed
Verify installation of combustion air inlet hoods and flue outlets per installation instructions
Verify installation of supply air thermistors per installation instructions (units with modulating gas, SCR electric or hydronic
heat only)
Verify that return-air filters and outdoor-air filters are in place and clean
Verify that unit is level within specified installation tolerances
Verify that fan wheels and propellers are properly positioned in the fan housing/orifice, and that all fan set screws are tight
Verify that fan bearing hold-down bolts and bearing race set screws are tight
Verify that fan sheaves are aligned and belts are properly tensioned
Verify that optional suction, discharge, and liquid service valves on each circuit are open
Verify that compressor crankcase heaters have been energized and functioning for 24 hours. (Caution: heaters will be hot to the
touch; take precautions to avoid burns.)
Signature __________________________________________________________________ Date ___________________________