Pre-Start-Up Checklist for 48/50N-Series Packaged Rooftop
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Controls, Start-Up, Operation, Service and Trouble-
shooting document.
I. Project Information
Job Name __________________________________________________________________________________________________
Address ____________________________________________________________________________________________________
City ___________________________________________________________ State ____________________ Zip ______________
Installing Contractor ________________________________________________________ Phone ___________________________
Equipment tag / Mark for ______________________________________________________________________________________
Sales Office _________________________________________________________________________________________________
Pre-Start-up Performed by _____________________________________________________ Phone __________________________
Unit Model (18 Chars) ____________________________________________ Serial (10 Chars) ____________________________
Design Information
Supply Airflow
(CFM)
II. Prestart-Up
Is there any physical damage?
Description _________________________________________________________________________________________________
___________________________________________________________________________________________________________
Verify that all packing materials have been removed from unit
Verify installation of economizer hoods per installation instructions
Verify installation of condensate drains and traps per installation instructions
Verify watertight interface between unit and curb (roof-mounted units)
Verify removal of supply fan shipping brackets per installation instructions
Verify removal of return fan shipping brackets (if equipped) per installation instructions
Verify compressor mounting bolt torque is 7 to 10 ft-lb. (9.5 to 13.5 n-m)
Verify installation of ductwork to unit or curb per installation instructions
Verify clearances around unit per installation instructions
Verify that power supply agrees with the unit nameplate
Verify that electrical power wiring is installed properly per installation instructions
Verify that unit is properly grounded per NEC/ETL
Verify installation of electrical disconnect per installation instructions
Verify that electrical circuit protection has been sized and installed properly per NEC/ETL
Verify that all terminals are tight
Verify that all plug assemblies are tight
Inspect all cables and thermistors for crossed wires and correct as needed
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53480165-01
(Remove and use for job file)
Return Air Temperature (RAT)
External Static
Pressure (ESP)
Dry Bulb (DB)
No
Yes
Printed in U.S.A.
Wet Bulb (WB)
If yes, has the trucking company been contacted?
Form 48-50N-7T
Supply Air
Temperature
Pg CL-1
12-2020
Condenser
Entering Air
Temperature
Yes
No
Replaces: 48-50N-6T

Advertisement

Table of Contents
loading

Table of Contents