3.11 Installing Driveline and Shielding
After installing the new cutterbar, you must reinstall the driveline and shielding. Refer to the procedure appropriate for
your machine:
• R113 –
3.11.1 Installing Driveline and Shielding on an R113 – Large Driven Drums, page 30
• R116 –
3.11.2 Installing Driveline and Shielding on an R116 – Small Driven Drums, page 33
3.11.1 Installing Driveline and Shielding on an R113 – Large Driven Drums
To reinstall the vertical driveline and shielding on the new cutterbar, follow these steps:
If you are installing the driveline on an R116, refer to
Drums, page
33.
NOTE:
3.3.1 Removing Driveline on an R113 – Large Driven Drums, page
Use parts retained from
1. Lubricate spindle splines (A). For specifications, refer to the
header/mower operator's manual or technical manual.
NOTE:
The driveline U-joints were greased at the factory and
considered to be lubricated for life. No further lubrication is
required.
NOTE:
For clarity, illustration shows cutaway view of drum and
tube shield.
2. Insert driveline (B) at an angle and guide it past hub
drive (C) and drum (D).
3. Insert splined spindle end (A) into the splined bore on
driveline (B).
4. Place a bead of medium-strength threadlocker
®
(Loctite
243 or equivalent) around the threads of four
M12 hex flange head bolts (A). Use the bolts and spacers to
secure driveline assembly (B) to hub drive (C). Torque bolts
to 102 Nm (75 lbf·ft).
214497
INSTALLATION INSTRUCTIONS
3.11.2 Installing Driveline and Shielding on an R116 – Small Driven
Figure 3.51: Driveline
Figure 3.52: Driveline
30
11.
C
D
A
B
A
C
A
B
Revision D