Magnefix MD4
5. SYSTEM COMMISSIONING AND

DECOMMISSIONING

The commissioning procedure for your Magnefix
switchgear is laid down in the Eaton general conditions of
sale or in the sales contract.
The full procedure is beyond the scope of this manual..
This paragraph deals with a number of general points.

5.1 Commissioning

Following manufacture and factory testing, acceptance
testing can take place on the basis of the IEC 62271-201
standard.
Acceptance testing is carried out at Eaton, in the presence
of the client and/or an independent testing authority (e.g.
KEMA [institute for approving electrical equipment]).
5.1.1

Acceptance testing

Acceptance testing includes:
Electrical checks on switching ON and OFF
Measuring the contact resistance values in the primary
circuit.
Withstand voltage testing of the primary circuit.
Discharge measurement.
Checking the proper operation of the overcurrent
indicators.
Operation of the position indicators, if installed.
Checking the proper operation of the mechanical
interlocks.
Checking the switch caps for proper operation.
Checking the vacuum circuit-breaker, if fitted, for
proper operation.
Visual inspection in order to establish whether the
configuration of materials is consistent with the order.
5.1.2

Inspections

After the switchgear has been set up, the inspections to be
carried out include the following (on the assumption that no
consumers are connected):
Measurements of voltage losses on the busbar
connections fitted on site.
Applying power to the installation in accordance with
IEC standard 62271-201.
Checking mechanical interlocks and satisfactory
switching on and switching off of the switch caps.
96
991.184 G01 03
The following points are not inspected:
Civil engineering work.
The connections of main and auxiliary cables (unless
carried out by or under the responsibility of Eaton.
Materials outside the scope of our supply.
5.1.3

Handover

Following these inspections, handover of the installation
can take place.
W
ARNING
All operations carried out after the handover are
no longer the responsibility of Eaton.
5.2 Decommissioning
The following safety measures must be taken when
dismantling the switchgear:
5.2.1

Dismantling

W
ARNING
Prior to dismantling, ensure that the entire
switchgear (primary and secondary) is dead.
C
AUTION
Broken epoxy resin has sharp edges.
The following safety precautions must be taken when
dismantling the switchgear:
During dismantling use protective equipment such as
safety goggles, gloves, protective footwear and dust
hoods.
Use suitable and safe tools.