Installation
6.7

Cable lead-through

In order to install/dismantle/adjust cables in the cable
lead-through, their protective cover needs to be disman-
tled and the five bolts have to be undone.
1. Disconnect the cable lead-through's protective
cover, which is secured with three bolts, see Im-
age 31.
2. Loosen the five screws on the cable grommet, see
Image 32. Cables can now be installed/removed/
adjusted in the grommet. On installation, the cable
must be installed together with existing cabling
with cable ties. Ensure the length of the cable is
sufficient for moving the control card. The outer
casing on cables connected to the control card
must be stripped 350 mm, see Image 33.
3. When all cables are correctly located in the cable
lead-through, tighten the five bolts, see Image 32.
Tightening torque: 5 Nm.
4. Install the cable lead-through's protective cover
with the three supplied bolts, see Image 31.
Tightening torque: 8 Nm.
www.zepro.com
Image 31. The cable lead-through's protec-
tive cover is secured with three bolts
Image 32. The cable lead-through's five bolts
Image 33. The outer sheathing on cable connected
to the control card must be stripped 350 mm.
Z 2500-130/150
350 mm.
25