Step 3 Move the UPS over its castors to the installation position.
Step 4 If the castors of the UPS need to be lifted from the ground, perform steps
Non-Secured
Step 5 Open the front and rear doors.
Step 6 Insert four M12x115 expansion bolts into the expansion bolt holes in the floor, and tighten the
expansion bolts.
Figure 4-4 Tightening expansion bolts
----End
Non-Secured Installation
Step 1 Lower the four anchor bolts at the bottom of the cabinet by using a wrench until all the four
castors at the bottom hang in the air, the anchor bolts bear the whole cabinet weight.
1. Wrench an anchor bolt clockwise to elevate a cabinet, or wrench an anchor bolt
2. To prevent cabinet tilting, adjust the four anchor bolts instead of one anchor bolt.
3. Use a measuring tape for measurement when leveling the cabinet to ensure that the height
4. Do not remove anchor bolts. Otherwise, you need to rework them for use.
Step 2 Check the cabinet levelness using a level. If the cabinet is not leveled, adjust the anchor bolts.
Issue 04 (2020-03-12)
Partially tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
Installation.
anticlockwise to lower it. The cabinet feet can be adjusted within a range of 0–8 mm.
between the cabinet top and the ground is 2000 mm + 3 mm.
Copyright © Huawei Technologies Co., Ltd.
4 Installation
Step 1
to
Step 2
in
57

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ups5000-e-60k-lasbs

Table of Contents