Chapter 5. Eclipse Edge Commissioning and Troubleshooting
Typical Commissioning Check Process
Table 5-1.
Step
Description
1
Physical installation
inspection
2
Antenna alignment
confirmation
3
Configuration
confirmation
4
Commissioning tests
5
Capturing as-built data
6
Final inspection and
sign-off
2
Procedure
A physical check prior to antenna alignment and node
configuration to ensure that the physical installation is
complete and correct.
An antenna alignment procedure is detailed in
Alignment for Edge on page 28
within 2.5 dB of calculated RSLs.
A check, using Portal, to ensure that terminal configurations
are complete and correct and that:
• The link is operating error-free.
• All relevant alarms are extinguished.
• Link performance data is as expected.
• IP addressing and routing is set correctly, which can be
confirmed from ProVision, where installed.
Tests designed to confirm correct link operation. Refer to
Eclipse Edge Commissioning Tests on page 3
Recording all relevant installation and performance data for
future reference. Refer to
on page 11
.
Completion of 'paperwork' recording installation hand-over for
operational use, and/or any remedial action needed to
complete an installation. Refer to
for Edge on page 11
.
Antenna
. Recorded RSLs should be
Commissioning Records for Edge
Commissioning Records
Aviat Networks
.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ECLIPSE EDGE and is the answer not in the manual?

Table of Contents

Save PDF