Step 8 Install the system subrack into the cabinet, as shown in
1.
2.
3.
Figure 5-29 Installing a system subrack
Step 9 Connect the cables that you removed to the system subrack in the same connection way.
Step 10 When the Power indicator is steady on, check whether the status of each component is
normal.
l
l
Step 11 Confirm the replacement.
1.
2.
Issue 05 (2019-01-30)
NOTE
Two different nameplates are included in the product. Select the one that contains identical information
to the nameplate on the removed system subrack.
Slide the system subrack into the cabinet along guide rails.
Use M6 screws to fix the system subrack in the cabinet.
Ensure that the system subrack is horizontally installed and tightly screwed.
If yes, the system subrack is successfully installed.
If no, cables are incorrectly connected, components are incorrectly installed, or the
newly installed system subrack is faulty.
Perform a post-replacement inspection.
After the parts replacement, return to the SmartKit page and click Replaced. Then
complete the check after the replacement as prompted.
Check system status.
On the Parts Replacement page, click Inspection to check the system status again. If
any inspection item fails, rectify the fault based on the suggestions in the inspection
report.
Copyright © Huawei Technologies Co., Ltd.
5 Replacing FRUs
Figure
5-29.
99

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

V300r001

Table of Contents