Chapter 4: Install Twisted-Pair Ports Cables
64
2. Remove the transceiver from its shipping container and store the
packaging material in a safe location.
3. Position the transceiver with its handle on the right and slide it into the
slot until it clicks into place. Refer to Figure 22.
Figure 22. Install SFP Transceiver
Note
If you are ready to attach the fiber optic cable to the transceiver,
continue with the next step. Otherwise, repeat steps 1 to 3 to install
the remaining transceivers in the switch.
4. Remove the dust cover from the transceiver. Refer to Figure 23.
Figure 23. Remove Dust Cover from SFP Transceiver