There are separate *.HEX files for the AT2000 CPK and the
power pack:
AT2000 CPK: AT2000CPK_Tool_Vxxx
Power pack: AT2000CPK_PowerPack_Vxxx
f Select the appropriate *.HEX file.
f In the window opened by the operating system, click on
the
Open
button.
; The
Start upload
button appears on the screen.
f Click on
Start
upload.
; The new firmware is uploaded.
; The progress bar shows progress of the data transfer in
percent (%).
; The AT2000 CPK display shows the current data transfer.
NOTE
Do not interrupt the connection during the data transfer. In
the event of an interruption, the AT2000 CPK will become
unusable and will need to be sent back to the manufacturer.

9 .6 .2 Change password

The setup specialist's password consists of four characters
and the default setting is 0000. HellermannTyton
recommends setting an alphanumeric password that includes
at least one special character.
f Click on Change.
f Enter the current password and click on
f Enter the new password and click on
f Re-enter the new password and click on
; The password is changed.

9 .6 .3 Update binding parameters

The update for the binding parameter settings
file ending ".cpkparam".
f Click on
Load from
file.
f Select the file.
f In the window opened by the operating system, click on
the
Open
button.
; The name of the file appears in
f Click on
Send to
tool.
; The new binding parameters are transmitted to the
AT2000 CPK.
; The progress bar shows progress of the data transfer in
percent (%).
Operating Instructions • AT2000 CPK • 07-2019 • v03 • 106-29004
OK
to confirm.
OK
to confirm.
OK
to confirm.
has the
3
File
loaded.

9 .6 .4 Install other languages

The update for languages which do not use Latin
characters, e.g. Asian languages, has the file ending
".bin".
f Click on
Load from
file.
f Select the file.
f In the window opened by the operating system, click on
the
Open
button.
; The name of the file appears in
f Click on
Send to
tool.
; The new languages are transmitted to the AT2000 CPK.
; The progress bar shows progress of the data transfer in
percent (%).
HT Data Management
File
loaded.