Connecting the media gateway to the main distribution
frame
Once the main distribution frame (MDF) is installed and wired, you must connect the media gateways to
the MDF.
Run excess cables on an upper cable ladder (if the MDF connectors are on top) or route them through a
cable slack manager that is placed next to the MDF. For more information, see
Managers
on page 183.
This section has information about

Equipment room cabling labels

Cable routing guidelines
Trunk cables among network interface, sneak fuse panel, and media gateway
And procedures for:
Installing cables between media gateway and main distribution frame
Installing connector cables between auxiliary cabinet (if used) and main distribution frame
page 189
Equipment room cabling labels
The purple port label shown in
both ends of the 25-pair cables connecting to the trunk/auxiliary field and/or distribution field.
Figure 64: Equipment room cabling labels
Figure notes
1
Purple Label (Port Cable)
2
Blue/Yellow Label (Building and
Floor)
Installing the Avaya S8500 Media Server with an Avaya G650 Media Gateway
December 2003

Connecting the media gateway to the main distribution frame

on page 185
on page 187
Figure 64, Equipment room cabling labels,
1 A 2
A
3
Yellow Label (Auxiliary)
4
Blue/Yellow Label (Site or
Satellite)
Installing Cable Slack
on page 189
on page 185 is installed on
labels LJK 060396
on page 189
on
185

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

G650

Table of Contents