Determining Your System Mounting Hole Layout - Allen-Bradley 1394 SERCOS Installation Manual

Multi-axis motion control system
Hide thumbs Also See for 1394 SERCOS:
Table of Contents

Advertisement

Allow 10.0 mm (0.4 in.) side clearance
Allow 25.4 mm (1.0 in.) clearance
at cover tab for opening and closing.
Allow additional clearance below the system module to provide the recommended cable bend radius. Refer
to the Motion Control Selection Guide (publication GMC-SG001x-EN-P) for more information.
Allen-Bradley PLCs
Figure 1.1
Minimum System and Axis Module Mounting Requirements
50.8 mm (2.0 in.) clearance
for airflow and installation
Status
DANGER
RISK OF ELECTRICAL SHOCK. HIGH VOLTAGE MAY
EXIST UP TO FIVE MINUTES AFTER REMOVING POWER.
Wire entry area for cable ground clamps
and signal, power, and motor connections.

Determining Your System Mounting Hole Layout

To prepare your subpanel for mounting:
1. Before you mount your 1394 System, use the following illustration
(refer to Figure 1.2) and table to identify your axis module
combination.
Installing Your 1394 SERCOS Interface System
Allow 10.0 mm (0.4 in.) side clearance
Allow 76.2 mm (3.0 in.) clearance
for depth of terminator.
1-5
Publication 1394-5.20 — July 2001